Launch
Strategy----Equipment and Telcom
|
1. Incorporate
|
2. Register Domain Name with InterNic
|
3. Set up Web Site with our Nework Access
Provider
|
4. Order Phone Lines(100) from phone company.
Install 1 Business and 1 Fax line, and 10 dial-in
lines(total of 12) for use at time site is
operational. Reserve 100 numbers.
|
5. Prepare facility with proper power and run
PVC for Ethernet cable and phone lines.
|
6. Order T-1 line from phone company. Get
confirmed date at time of order--(Make entire
order contingent upon install date.)
|
7. Visit sources for purchasing equipment:
|
8. Upon confirmation of Telcom Install
Completion Date, contact equipment supplier(1 1/2
weeks) prior to the aforementioned completion date,
and order and install equipment: i.e. Servers,
CSU/DSU, monitors, keyboards, etc.
|
9. Contact Network Access Provider(72 hours)
prior to final Install Phase, to configure and set
up our Gateway and Equipment. i.e. Router, CSU/DSU.
|
10. Soak the system. (1 to 2 weeks) or less...
|
11. Official Operational Phase.
|
|